INSTALLATION OF LIFTS AT PEDESTRIAN OVERHEAD BRIDGE ALONG SENGKANG EAST DRIVE AND INSTALLING LIFTS AT MORE BRIDGES

MP Louis Chua

Mr Chua Kheng Wee Louis asked the Minister for Transport (a) whether site feasibility studies conducted on the installation of lifts at the Pedestrian Overhead Bridge (POB 60020) along Sengkang East Drive suggest that it is technically feasible to install such lifts; (b) which other Government agencies are required to approve such an installation and what are the deadlines given for such approvals; and (c) what is the estimated timeline for the tender and completion of the construction of the lifts.

Mr Chee Hong Tat: Under the current phase of the Land Transport Authority’s (LTA’s) lift retrofitting programme, LTA will be prioritising the retrofitting of Pedestrian Overhead Bridges (POBs) with lifts at locations that will benefit a larger number of seniors, including this POB at Sengkang East Drive. 

It takes up to 22 months to retrofit a POB to include lifts. LTA will need to seek approvals from agencies, such as the Building and Construction Authority, the National Environment Agency, The National Parks Board, the Public Utilities Board and the Urban Redevelopment Authority, before commencing works. 

Ministry of Transport
3 April 2024